2019 Street Reconstruction – Project Schedule

2019 Street Reconstruction – Project Schedule (08/05/2019-08/09/2019)

The construction season has begun in The Village of Allouez on some or all of the streets listed below:

1. Longview Ave. –Delahaut St. to Libal St.
2. Oakwood Ave. – Greene Ave. to Allouez Ave.
3. Oak Hill Dr. – Beaumont St. to Oakwood Ave.
4. Summit St. – Beaumont St. to Oakwood Ave.
5. Martha Ave. – Dead End south 60 feet (New Construction)
6. St. Joseph St. – Riverside Dr. to Webster Ave.

This reconstruction project includes:

– Replacement of the existing water main, sanitary and storm sewer where necessary.
– Removal and replacement of existing water, sanitary and storm sewer laterals to the property line.
– Placement of new concrete curb & gutter and driveway aprons. The existing driveway width at the property line will be matched.
– Removal and replacement of the asphalt pavement.
– Installation of new sidewalk on Longview Ave (north side only) and St. Joseph St. (both sides).
– Voluntary replacement of private side sanitary sewer lateral.

Longview Ave. – Delahaut St. to Libal St.
Weather permitting the anticipated project schedule is as follows:
• Work Started – June 24
• Substantial Completion Date – End of August

Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction. Temporary mailboxes are set up for use. Concrete curb and gutter to cure until Wednesday then work on the driveway aprons and sidewalk to begin. Estimated to be completed by weeks end.

Martha Ave. – Dead End south 60 feet (New Construction)
• Work Started – May 13th
• Substantial Completion Date – End of August

Project Status:
Work on the road excavation and concrete curb and gutter to take place this week. Estimated to be completed by weeks end.

St. Joseph St. – Riverside Dr. to Webster Ave.
Weather permitting the anticipated project schedule is as follows:
• Work Started– May 20th
• Substantial Completion Date – Middle of September

Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction.   Turf restoration will continue until completed later in the week with concrete work to be finalized on Monday. Final paving to be scheduled after black ground is placed and manhole adjustments are made.

Oakwood Ave. – Greene Ave. to Mission Road
Weather permitting the anticipated project schedule is as follows:
• Work Started June 24
• Substantial Completion Date – Middle to end of October

Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction. Temporary mailboxes are set up for use. The installation of water services and sanitary sewer lateral will continue north towards Mission Road until mid-week. Storm sewer installation at the Greene Avenue intersection would be next on the schedule and planned for Wednesday/Thursday. Temporary water set-up on Oakwood between Whitney and Mission is tentatively set for Thursday/Friday. Private side sanitary sewer lateral installation is set to begin early next week. Pre-installation visits to begin this week.

Oakwood Ave. –Mission Road to Allouez Ave.
Weather permitting the anticipated project schedule is as follows:
• Work to Begin – Approximately 9/3/19.
• Substantial Completion Date – Middle to end of October

Project Status:

Work has not started

Oak Hill Dr. – Beaumont St. to Oakwood Ave.
Weather permitting the anticipated project schedule is as follows:
• Work to Begin – Approximately 8/12/19.
• Substantial Completion Date – Middle to end of October

Project Status:
Road is set to be pulverized towards the end of the week. Temporary water set-up on Oak Hill Road between Beaumont and Oakwood is tentatively set for Thursday/Friday

Summit St. – Beaumont St. to Oakwood Ave.
Weather permitting the anticipated project schedule is as follows:
• Work to Begin – Approximately 8/28/19
• Substantial Completion Date – Middle to end of October

Project Status:
Work has not started.