2019 Street Reconstruction – Project Schedule

September 19, 2019

The construction season has begun in The Village of Allouez on some or all of the streets listed below:

  1. Longview Ave. –Delahaut St. to Libal St.
  2. Oakwood Ave. – Greene Ave. to Allouez Ave.
  3. Oak Hill Dr. – Beaumont St. to Oakwood Ave.
  4. Summit St. – Beaumont St. to Oakwood Ave.
  5. Martha Ave. – Dead End south 60 feet (New Construction)
  6. St. Joseph St. – Riverside Dr. to Webster Ave.
  7. Brookridge St. – Libal St. to Dauphin St.
  8. Beaupre St. – Libal St. to Webster Ave.
  9. Warren Court – Riverside Dr. to Du Charme Ln.

This reconstruction project includes:

  • Replacement of the existing water main, sanitary and storm sewer where necessary.
  • Removal and replacement of existing water, sanitary and storm sewer laterals to the property line.
  • Placement of new concrete curb & gutter and driveway aprons. The existing driveway width at the property line will be matched.
  • Removal and replacement of the asphalt pavement.
  • Installation of new sidewalk on Longview Ave (north side only) and St. Joseph St. (both sides).
  • Voluntary replacement of private side sanitary sewer lateral.

Longview Ave. – Delahaut St. to Libal St.

  • Work Started – June 24
  • Work Completed – September 6

Project Status:

Street opened to traffic.  Contractor to complete Punchlist items and to monitor the progress of the turf restoration.

Martha Ave. – Dead End south 60 feet (New Construction)

  • Work Started – May 13th
  • Work Completed – September 13

Project Status:

Street opened to traffic.  Contractor to complete Punchlist items and to monitor the progress of the turf restoration.

St. Joseph St. – Riverside Dr. to Webster Ave.

  • Work Started– May 20th
  • Work Completed

Project Status:

Street opened to traffic.  Contractor to complete Punchlist and to monitor the progress of the turf restoration.

Oakwood Ave. – Greene Ave. to Mission Road

Weather permitting the anticipated project schedule is as follows:

  • Work Started June 24
  • Substantial Completion Date – Middle to end of October

Project Status:

Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction.  Temporary mailboxes are set up for use.

Curb & gutter installation to begin this week with driveway aprons & turf restoration to follow.

Oakwood Ave. –Mission Road to Allouez Ave.

Weather permitting the anticipated project schedule is as follows:

  • Work Started – Sept 3
  • Substantial Completion Date – Middle to end of October

Project Status:

Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction.  Temporary mailboxes are set up for use.

The contractor will be working on water services and sanitary sewer laterals this week with storm sewer main line to follow. Private side sanitary sewer lateral installation is scheduled for next week.

Oak Hill Dr. – Beaumont St. to Oakwood Ave.

Weather permitting the anticipated project schedule is as follows:

  • Work started Aug 12
  • Substantial Completion Date – Middle to end of October

Project Status:

Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction.

Road excavation to begin with curb & gutter to follow

Summit St. – Beaumont St. to Oakwood Ave.

Weather permitting the anticipated project schedule is as follows:

  • Work Started Aug 28
  • Substantial Completion Date – Middle to end of October

Project Status:

Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction.

Private side sanitary sewer lateral installation is scheduled for this week. with street excavation to follow.

Brookridge St. – Libal St. to Dauphin St.

  • Work Started — August 19
  • Work Completed – September 7

Project Status:

Street opened to traffic

Beaupre St. – Libal St. to Webster Ave.

Weather permitting the anticipated project schedule is as follows:

  • Work to Begin – Approximately 9/23/19
  • Substantial Completion Date – Middle to end of October

Project Status:

Work has not started.

Warren Court – Riverside Dr. to Du Charme Ln.

Weather permitting the anticipated project schedule is as follows:

  • Work to Begin – Approximately 9/23/19
  • Substantial Completion Date – Middle to end of October

Project Status:

Work has not started.

Thank you,

Jeff Piette             
Engineering Technician 
Ph. 920-448-2800, Ext. 122
jeff@villageofallouez.com

Sean Gehin, P.E.
Director of Public Works
Ph. 920-448-2800 Ext. 108
seang@villageofallouez.com