2019 Street Reconstruction – Project Schedule

October 21, 2019

The construction season has begun in The Village of Allouez on some or all of the streets listed below:

1. Longview Ave. –Delahaut St. to Libal St.
2. Oakwood Ave. – Greene Ave. to Allouez Ave.
3. Oak Hill Dr. – Beaumont St. to Oakwood Ave.
4. Summit St. – Beaumont St. to Oakwood Ave.
5. Martha Ave. – Dead End south 60 feet (New Construction)
6. St. Joseph St. – Riverside Dr. to Webster Ave.
7. Brookridge St. – Libal St. to Dauphin St.
8. Beaupre St. – Libal St. to Webster Ave.
9. Warren Court – Riverside Dr. to Du Charme Ln.
10. Blackhawk Drive – Libal Street east 250 ft.

This reconstruction project includes:

– Replacement of the existing water main, sanitary and storm sewer where necessary.
– Removal and replacement of existing water, sanitary and storm sewer laterals to the property line.
– Placement of new concrete curb & gutter and driveway aprons. The existing driveway width at the property line will be matched.
– Removal and replacement of the asphalt pavement.
– Installation of new sidewalk on Longview Ave (north side only) and St. Joseph St. (both sides).
– Voluntary replacement of private side sanitary sewer lateral.

Longview Ave. – Delahaut St. to Libal St.
• Work Started – June 24
• Work Completed – September 6

Project Status:
Street opened to traffic. Contractor will monitor the progress of the turf restoration. Lawns to be mowed as needed by property owners

Martha Ave. – Dead End south 60 feet (New Construction)
• Work Started – May 13th
• Work Completed – September 13

Project Status:
Street opened to traffic. Contractor will monitor the progress of the turf restoration. Lawns to be mowed as needed by property owners

St. Joseph St. – Riverside Dr. to Webster Ave.
• Work Started– May 20th
• Work Completed

Project Status:
Street opened to traffic. Contractor will monitor the progress of the turf restoration. Lawns to be mowed as needed by property owners.

Oakwood Ave. – Greene Ave. to Mission Road
Weather permitting the anticipated project schedule is as follows:
• Work Started June 24
• Work completed

Project Status:
Road is paved and open to traffic, final layer of asphalt to be installed in spring of 2020. Contractor will monitor the progress of the turf restoration. Lawns to be mowed as needed by property owners.

Oakwood Ave. –Mission Road to Allouez Ave.
Weather permitting the anticipated project schedule is as follows:
• Work Started – Sept 3
• Substantial Completion Date – Extended to November 8, 2019

Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction. Temporary mailboxes are set up for use.

Curbing to be installed mid-week with driveway aprons to follow. Paving & landscaping scheduled for the week of Oct.28.

Oak Hill Dr. – Beaumont St. to Oakwood Ave.
Weather permitting the anticipated project schedule is as follows:
• Work started Aug 12
• Work completed

Project Status:
Road is paved and open to traffic, final layer of asphalt to be installed in spring of 2020. Contractor will monitor the progress of the turf restoration. Lawns to be mowed as needed by property owners.

Summit St. – Beaumont St. to Oakwood Ave.
Weather permitting the anticipated project schedule is as follows:
• Work Started Aug 28
• Work completed

Project Status:
Road is paved and open to traffic, final layer of asphalt to be installed in spring of 2020. Contractor will monitor the progress of the turf restoration. Lawns to be mowed as needed by property owners.

Brookridge St. – Libal St. to Dauphin St.
• Work Started — August 19
• Work Completed – September 7

Project Status:
Street opened to traffic. Contractor will monitor the progress of the turf restoration. Lawns to be mowed as needed by property owners

Beaupre St. – Libal St. to Webster Ave.
Weather permitting the anticipated project schedule is as follows:
• Work to Begin – September 23
• Work Completed

Project Status:
Street opened to traffic. Contractor will monitor the progress of the turf restoration. Lawns to be mowed as needed by property owners

Warren Court – Riverside Dr. to Du Charme Ln.
Weather permitting the anticipated project schedule is as follows:
• Work to Begin – Approximately 9/23/19
• Substantial Completion Date – November 1, 2019

Project Status:
Driveway aprons to be installed with paving & restoration to follow.

Blackhawk Drive – Libal Street east 250 feet.
Weather permitting the anticipated project schedule is as follows:
• Work Started October 2nd
• Substantial Completion Date – November 1st, 2019

Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes and residents during construction.  Roadway excavation and concrete curb and gutter scheduled for this week. Grading and paving with turf restoration to follow.

Thank you,

Jeff Piette             
Engineering Technician 
Ph. 920-448-2800, Ext. 122
jeff@villageofallouez.com

Sean Gehin, P.E.
Director of Public Works
Ph. 920-448-2800 Ext. 108
seang@villageofallouez.com