2020 Reconstruction Project Update (May 18, 2020)

2020 Street Reconstruction – Project Schedule
May 18, 2020-May 22, 2020

This 2020 construction season has begun in The Village of Allouez on some or all of the streets listed below:

1. St Mary’s Boulevard — Riverside Dr to ± 1500 feet to east (#310/#311)
2. Stanton Court/Arbor Lane — Stanton Ct to Rosemont Dr (near Webster Ave)
3. Garland Street – Webster Ave to Baird St
4. Allouez Terrace Alley – Riverside Dr to end.
5. East St Joseph Alley behind Associated Bank
6. Olde River Condominium Trail
7. Longview Pond Trail Repair

These resurfacing projects include:
– Removal and replacement of the asphalt pavement.
– Replacement of defective gravel base
– Placement of defective concrete curb & gutter and driveway aprons
– Manhole & catch basin repairs
– Sanitary sewer repairs on St Mary’s Blvd

1. St Mary’s Boulevard – Riverside Dr to ± 1500 feet to east (#310/#311)
Weather permitting the anticipated project schedule is as follows:
• Work started – May 7
• Substantial Completion Date – Beginning of June (paving only/sanitary work will continue)

Project Status:
Fischer Concrete will continue to remove & replace defective curbing & aprons thru mid-week. Asphalt removal to follow.

2. Stanton Court/Arbor Lane — Stanton Ct to Rosemont Dr (near Webster Ave)
Weather permitting the anticipated project schedule is as follows:
• Work started – May 13
• Substantial Completion Date – Early June

Project Status:
Fischer Concrete will be in mid-week to remove & replace defective curbing & aprons. Asphalt removal to follow.

3. Garland Street – Webster Ave to Baird St
Weather permitting the anticipated project schedule is as follows:
• Work to begin – May 20th
• Substantial Completion Date – Early June

Project Status:
Work has not started.

4. Allouez Terrace Alley – Riverside Dr to end.
Weather permitting the anticipated project schedule is as follows:
• Work started – May 14 (asphalt removal)
• Substantial Completion Date – Early June

Project Status:
The asphalt has been removed, the roadway is gravel and usable. Grading & paving is scheduled for the week of May 25-29

5. East St Joseph Alley behind Associated Bank
Weather permitting the anticipated project schedule is as follows:
• Work started – May 14 (asphalt removal)
• Substantial Completion Date – Early June

Project Status:
The asphalt has been removed, the roadway is gravel and usable. Grading & paving is scheduled for the week of May 25-29

6. Olde River Condominium Trail
Weather permitting the anticipated project schedule is as follows:
• Work to Begin – May 18
• Substantial Completion Date – Early June

Project Status:
Work has not started.

Completion of 2019 projects

Final paving of Oakwood, Oak Hill, Summit and Blackhawk is scheduled to begin Thursday May 21st.

Sean Gehin, P.E. Director of Public Works
Ph. 920-448-2800, Ext. 108