2020 Reconstruction Project Update (June 22, 2020)

2020 Street Reconstruction – Project Schedule
June 22, 2020-June 26, 2020

 

This 2020 construction season has begun in The Village of Allouez on some or all of the streets listed below:

1. St Mary’s Boulevard — Riverside Dr to ± 1500 feet to east (#310/#311)
2. Stanton Court/Arbor Lane — Stanton Ct to Rosemont Dr (near Webster Ave)
3. Garland Street – Webster Ave to Baird St
4. Allouez Terrace Alley – Riverside Dr to end.
5. East St Joseph Alley behind Associated Bank
6. Olde River Condominium Trail
7. Longview Pond Trail Repair

These resurfacing projects include:
– Removal and replacement of the asphalt pavement.
– Replacement of defective gravel base
– Replacement of defective concrete curb & gutter and driveway aprons
– Manhole & catch basin repairs
– Sanitary sewer repairs on St Mary’s Blvd

1. St Mary’s Boulevard – Riverside Dr to ± 1500 feet to east (#310/#311)
Weather permitting the anticipated project schedule is as follows:
• Work started – May 7
• Substantial Completion Date – Beginning of June (paving only/sanitary work will continue)

Project Status:
Initial paving completed sewer work to follow. Turf restoration likely the week of June 22 with final paving in early fall after the sewer work has been completed.

2. Stanton Court/Arbor Lane — Stanton Ct to Rosemont Dr (near Webster Ave)
Weather permitting the anticipated project schedule is as follows:
• Work started – May 13
• Substantial Completion Date – Early June

Project Status:
Final paving completed, turf restoration the week of June 22.

3. Garland Street – Webster Ave to Baird St
Weather permitting the anticipated project schedule is as follows:
• Work started – May 28
• Substantial Completion Date – Early June

Project Status:
Final paving completed, turf restoration the week of June 22

4. Allouez Terrace Alley – Riverside Dr to end.
Weather permitting the anticipated project schedule is as follows:
• Work started – May 14
• Substantial Completion Date – Early June

Project Status:
Paving completed restoration to follow.

5. East St Joseph Alley behind Associated Bank
Weather permitting the anticipated project schedule is as follows:
• Work started – May 14 (asphalt removal)
• Substantial Completion Date – Early June

Project Status:
Paving completed restoration to follow.

6. Olde River Condominium Trail
Weather permitting the anticipated project schedule is as follows:
• Work to Begin as weather permits
• Substantial Completion Date – Early June

Project Status:
Trail paving completed, gravel shoulder and turf restoration to follow.

Completion of 2019 projects

Final paving of Oakwood, Oak Hill, Summit and Blackhawk is completed.